Question thread · 2 questions
What the estimated final cost is of the Borders Railway project.
Started with S4W-22201 on 28 Jul 2014; latest 19 Aug 2014. Each later question says it follows up an earlier answer.
Follow-ups
1
Span
22 days
Answered
2 of 2
Asked by
1
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Government what the estimated final cost is of the Borders Railway project.
Keith Brown, 7 Aug 2014: The target cost of constructing the project agreed with Network Rail is £294 million (at 2012 prices). -
further to the answer to question S4W-22201 by Keith Brown on 7 August 2014, how much (a) the Galashiels transport interchange, (b) the resurfacing of the B6458, (c) other essential work and (d) work not in the remit of Network Rail will add to the final cost.
Keith Brown, 5 Sep 2014: The target cost of constructing the project agreed with Network Rail is £294 million (at 2012 prices). Under this target cost arrangement the final cost of construction will not be known until completion. Transport Scotland remains confident of meeting the target cost. Galashiels transport interchange and the resurfac…
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.