 further to the answer to question S4W-22201 by Keith Brown on 7 August 2014, how much (a) the Galashiels transport interchange, (b) the re…

Answered Asked by John Lamont Con Lodged 19 Aug 2014

The question

To ask the Scottish Government, further to the answer to question S4W-22201 by Keith Brown on 7 August 2014, how much (a) the Galashiels transport interchange, (b) the resurfacing of the B6458, (c) other essential work and (d) work not in the remit of Network Rail will add to the final cost.

The answer

Answered by Keith Brown on 5 Sep 2014 · 17 days after it was lodged, on time

The target cost of constructing the project agreed with Network Rail is £294 million (at 2012 prices). Under this target cost arrangement the final cost of construction will not be known until completion. Transport Scotland remains confident of meeting the target cost.
Galashiels transport interchange and the resurfacing of the B6458 are not funded by this project.