What consultants it hired for advice about the new Caledonian sleeper rail franchise; how much each was paid; whether they were asked to declare any possible conflicts of interest and, if so, what declarations were made.

Started with S4W-21657 on 5 Jun 2014; latest 19 Jun 2014. Each later question says it follows up an earlier answer.

Follow-ups
3
longest chain 1 step
Span
14 days
5 Jun 2014 to 19 Jun 2014
Answered
4 of 4
by Keith Brown
Asked by
1
John Finnie

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S4W-21657 5 Jun 2014 John Finnie Ind Answered

    To ask the Scottish Government what consultants it hired for advice about the new Caledonian sleeper rail franchise; how much each was paid; whether they were asked to declare any possible conflicts of interest and, if so, what declarations were made.

    Keith Brown, 17 Jun 2014: The requirement for a procurement competition for rail franchising in Scotland occurs once every 7-10 years, and it is not therefore economically advantageous to continually employ, train and retain the specialist staff required in order to provide advice on undertaking such procurement competitions. Scottish Minister…
  2. S4W-21845 19 Jun 2014 John Finnie Ind Answered

    What procurements the term "both procurements" refers to.

    Keith Brown, 11 Jul 2014: ‘Both procurements’ in the context of the answer to question S4W-21657 refers to the Caledonian Sleeper Franchise procurement (which has now been awarded and is now in mobilisation) and the ongoing ScotRail Franchise procurement.
  3. S4W-21846 19 Jun 2014 John Finnie Ind Answered follows S4W-21657

    When the costs of the procurement will be finalised and where that information will be published.

    Keith Brown, 11 Jul 2014: Further to the answer to question S4W-21657 the costs of the procurement, mobilisation and transition will be finalised after 31 March 2015 when the new Caledonian Sleeper Franchise begins. This information will be made available once it is finalised.
  4. S4W-21847 19 Jun 2014 John Finnie Ind Answered follows S4W-21657

     further to the answer to question S4W-21657 by Keith Brown on 17 June 2014, how the Parliament will be made aware if any conflicts of interest are identified.

    Keith Brown, 11 Jul 2014: Further to the answer to S4W-21657 officials at Transport Scotland actively monitor these matters on a regular basis. Were there to be any actual conflicts identified, and if considered appropriate, the Scottish Government would inform Parliament.

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.

All question threads