Parliament Workbench

Question thread · 2 questions

What progress is being made toward the reopening of Kintore railway station.

Started with S4W-19597 on 4 Feb 2014; latest 27 May 2015. Each later question says it follows up an earlier answer.

Follow-ups
1
longest chain 1 step
Span
477 days
4 Feb 2014 to 27 May 2015
Answered
2 of 2
by Keith Brown, Derek Mackay
Asked by
2
MSPs

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S4W-19597 4 Feb 2014 Dennis Robertson SNP Answered

    To ask the Scottish Government what progress is being made toward the reopening of Kintore railway station.

    Keith Brown, 20 Feb 2014: As specified in the Scottish Government's High Level Output Specification (HLOS) in 2012, Kintore Station forms part of phase one of the Aberdeen to Inverness Rail Improvements Project. Delivery of phase one is anticipated to begin in 2016 and will be completed by 2019. Kintore Station will only be able to operate aft…
  2. S4W-25764 27 May 2015 Nanette Milne Con Answered

    Whether it will provide an update on when it expects Kintore railway station to reopen.

    Derek Mackay, 10 Jun 2015: I can confirm that Network Rail have been working with promoters, Nestrans (the north east regional transport partnership) and Aberdeenshire council on the design of Kintore station, which includes car parking and road access. Transport Scotland will be meeting Network Rail and promoters later in 2015. This meeting wi…

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.

All question threads