Parliament Workbench
Data: Motions & questions to 3 Dec 2026

Written Question · S4W-25764 · Session 4

Further to the answer to question S4W-19597 by Keith Brown on 20 February 2014, whether it will provide an update on when it expects Kintor…

Answered Asked by Nanette Milne Con Lodged 27 May 2015

The question

To ask the Scottish Government, further to the answer to question S4W-19597 by Keith Brown on 20 February 2014, whether it will provide an update on when it expects Kintore railway station to reopen.

The answer

Answered by Derek Mackay on 10 Jun 2015 · 14 days after it was lodged, on time

I can confirm that Network Rail have been working with promoters, Nestrans (the north east regional transport partnership) and Aberdeenshire council on the design of Kintore station, which includes car parking and road access. Transport Scotland will be meeting Network Rail and promoters later in 2015. This meeting will include discussion of emerging proposals on third party funding, design and development of the station. Accordingly, the delivery of Kintore station remains on schedule for completion by March 2019.

In the Official Report

No contribution in the Official Report cites S4W-25764 by reference.