What the reasons are for reported delays in projects due to proceed in 2012-13 through the non-profit distribution programme, broken down by project.
Started with S4W-12698 on 30 Jan 2013; latest 7 Mar 2013. Each later question says it follows up an earlier answer.
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Government what the reasons are for reported delays in projects due to proceed in 2012-13 through the non-profit distribution programme, broken down by project.
Nicola Sturgeon, 25 Feb 2013: The Non-Profit Distributing (NPD) programme was announced in November 2010, as part of the Spending Review 2010. It was a response to the reduction in traditional capital Departmental Expenditure Limits (DEL) originally set at 36% in real terms over the four years of the UK Spending Review. NPD provides an alternative… -
When it will publish the timescale for the delivery of each of the 19 schools projects in Phase 3.
Nicola Sturgeon, 18 Mar 2013: Scotland’s Schools for the Future Programme, of which these 19 schools are a part, will see the delivery of 67 new or refurbished schools across all parts of Scotland by March 2018. So far six schools have been completed, nine schools are currently under construction of which five are expected to open in August 2013. … -
What funding has been made available for each school project that has been delayed by project-specific issues.
Nicola Sturgeon, 18 Mar 2013: Scotland’s Schools for the Future Programme is a joint £1.25 billion programme with Scotland’s local authorities which will see the delivery of 67 new or refurbished schools across all parts of Scotland. The Scottish Government is contributing £800 million towards the programme and the local authorities £450 million. … -
Whether any school projects will be delivered through the HUB initiative and, if so, which projects.
Nicola Sturgeon, 18 Mar 2013: All revenue funded HUB school projects delivered through the Schools for the Future Programme are published within the “Pipeline of Revenue Funded Projects” on the Scottish Futures Trust website which is regularly updated and can be obtained via the following link: http://www.scottishfuturestrust.org.uk/publications/p… -
If staggering the timing of procurement of the three colleges avoided them competing with each other in the market, for what reason the colleges will now move into construction around the same time.
Nicola Sturgeon, 18 Mar 2013: The staggered timing of procurement took account of potential market capacity constraints in the bidding process and the ability of contractors to participate in the bidding process for more than one project. There are no overall capacity constraints in the market for delivering the construction of these projects. -
Whether moving the colleges into construction around the same time might have a detrimental effect, and what the reasons are for its position on this matter.
Nicola Sturgeon, 18 Mar 2013: There is no detrimental effect of the colleges moving into construction around the same time as overall capacity in the construction market to deliver these projects is not constrained. The projects differ in location and or size, and have attracted interest from different contractors and will ultimately be delivered … -
How the staggered timing for college projects has been prioritised.
Nicola Sturgeon, 18 Mar 2013: Prioritisation was based on the previous development of the projects and the preparedness of their business cases for receiving approval. -
Which minister approved the decision to deliver the Borders Railway project using Network Rail’s Regulatory Asset Base and not the non-profit distributing model, and for what reason Network Rail’s Regulatory Asset Base was chosen as the preferred method.
Nicola Sturgeon, 18 Mar 2013: The Minister for Transport and Veterans approved the decision to deliver the Borders Railway using Network Rail’s Regulatory Asset Base. Transport Scotland cancelled the original non-profit distributing procurement competition in September 2011 following the withdrawal of two of the three bidders. Network Rail confirm…
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.