Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S4W-13527 · Session 4

Further to the answer to question S4W-12698 by Nicola Sturgeon on 25 February 2013, when it will publish the timescale for the delivery of …

Answered Asked by Richard Baker Lab Lodged 7 Mar 2013

The question

To ask the Scottish Government, further to the answer to question S4W-12698 by Nicola Sturgeon on 25 February 2013, when it will publish the timescale for the delivery of each of the 19 schools projects in Phase 3.

The answer

Answered by Nicola Sturgeon on 18 Mar 2013 · 11 days after it was lodged, on time

Scotland’s Schools for the Future Programme, of which these 19 schools are a part, will see the delivery of 67 new or refurbished schools across all parts of Scotland by March 2018. So far six schools have been completed, nine schools are currently under construction of which five are expected to open in August 2013.
The delivery timescales of all revenue funded schools through the Schools for the Future Programme are published within the “Pipeline of Revenue Funded Projects” on the Scottish Futures Trust website which is regularly updated and can be obtained via the following link:
http://www.scottishfuturestrust.org.uk/publications/pipeline-of-revenue-funded-projects-npd-and-hub-october-2012/.

In the Official Report

No contribution in the Official Report cites S4W-13527 by reference.