Question thread · 3 questions

What projects are to be supported by the South West hubco.

Started with S4W-05256 on 25 Jan 2012; latest 25 Jun 2012. Each later question says it follows up an earlier answer.

Follow-ups
2
longest chain 2 steps
Span
152 days
25 Jan 2012 to 25 Jun 2012
Answered
3 of 3
by Alex Neil
Asked by
1
Margaret McCulloch

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S4W-05256 25 Jan 2012 Margaret McCulloch Lab Answered

    To ask the Scottish Executive what projects are to be supported by the South West hubco.

    Alex Neil, 8 Feb 2012: I have asked Scottish Futures Trust to respond. The response is as follows: The following projects were named in the Prequalification Questionnaire for the South West hub. Project Name Description Montrose House Care home on Arran Stevenson Institute Multi-agency health unit of Largs Irvine East Primary School New unn…
  2. S4W-07855 12 Jun 2012 Margaret McCulloch Lab Answered

    What progress has been made toward completion of each of the projects named in the questionnaire.

    Alex Neil, 25 Jun 2012: The South West hub Territory’s current pipeline contains twenty five projects from 11 of the 19 participants with an estimated construction cost totalling over £250 million. These projects are currently being developed by the relevant participant bodies ahead of the appointment of a preferred Private Sector Developmen…
  3. S4W-08261 25 Jun 2012 Margaret McCulloch Lab Answered

    What progress has been made toward completion of (a) East Kilbride Hunter Health Centre, (b) Wishaw Health Centre and (c) Kilsyth Health Centre and what the estimated completion dates are.

    Alex Neil, 9 Jul 2012: The South West hubco is due to be formally established in October 2012. Once the hubco is formed, the projects referred to in the question will be developed in accordance with the NHS Board's requirements. In advance of this delivery phase, an Initial Agreement for the three projects was approved by the Scottish Gover…

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.

All question threads