Further to the answer to question S4W-05256 by Alex Neil on 8 February 2012, what progress has been made toward completion of each of the p…
The question
To ask the Scottish Executive, further to the answer to question S4W-05256 by Alex Neil on 8 February 2012, what progress has been made toward completion of each of the projects named in the questionnaire.
The answer
The South West hub Territory’s current pipeline contains twenty five projects from 11 of the 19 participants with an estimated construction cost totalling over £250 million.
These projects are currently being developed by the relevant participant bodies ahead of the appointment of a preferred Private Sector Development Partner (PSDP) in August 2012 and the subsequent planned hubco creation in October 2012.
It is thereafter expected that these projects will be delivered by the hubco in accordance with the individual participant timescales.
The procurement of the PSDP is on schedule and final tenders were received on 19 June 2012.
These projects are currently being developed by the relevant participant bodies ahead of the appointment of a preferred Private Sector Development Partner (PSDP) in August 2012 and the subsequent planned hubco creation in October 2012.
It is thereafter expected that these projects will be delivered by the hubco in accordance with the individual participant timescales.
The procurement of the PSDP is on schedule and final tenders were received on 19 June 2012.