Question thread · 2 questions
By what means the Borders railway project will be funded.
Started with S3W-35085 on 2 Jul 2010; latest 3 Aug 2010. Each later question says it follows up an earlier answer.
Follow-ups
1
Span
32 days
Answered
2 of 2
Asked by
1
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Executive by what means the Borders railway project will be funded.
Stewart Stevenson, 26 Jul 2010: The Borders railway line will be designed, built, financed and maintained by a newly created, Transport Scotland-backed company, using a design, build, finance and maintenance contract and will use the Scottish Government''s non-profit distributing procurement model as developed by the Scottish Futures Trust. -
From what sources the money will come to finance the Borders railway line; what the expected rate of interest is on the borrowing; what recourse there will be to private finance; how much public money will be used, and from what sources.
Stewart Stevenson, 1 Sep 2010: The successful Design, Build, Finance and Maintenance (DBFM) Contractor is required to obtain appropriate private finance to fund the activities of the DBFM Contract. The cost of capital will form part of each consortium''s bid, and therefore the expected cost of capital is commercially confidential. The DBFM contract…
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.