Further to the answer to question S3W-35085 by Stewart Stevenson on 26 July 2010, from what sources the money will come to finance the Bord…

Answered Asked by George Foulkes Lab Lodged 3 Aug 2010

The question

To ask the Scottish Executive, further to the answer to question S3W-35085 by Stewart Stevenson on 26 July 2010, from what sources the money will come to finance the Borders railway line; what the expected rate of interest is on the borrowing; what recourse there will be to private finance; how much public money will be used, and from what sources.

The answer

Answered by Stewart Stevenson on 1 Sep 2010 · 29 days after it was lodged, 1 day after it was due

The successful Design, Build, Finance and Maintenance (DBFM) Contractor is required to obtain appropriate private finance to fund the activities of the DBFM Contract. The cost of capital will form part of each consortium''s bid, and therefore the expected cost of capital is commercially confidential. The DBFM contract is the principal source of finance for the project, and will be managed using Not for Profit Distributing principles. DBFM payments will be made by the Scottish Government over a thirty year period following the opening of the railway. In addition, the Scottish Government has spent to date £52 million on land purchase, advanced works and development costs. The City of Edinburgh, Midlothian and Scottish Borders Councils will also make a capped financial contribution worth in total £30 million.