What current or proposed rail projects have a higher benefit cost ratio than the Glasgow Airport Rail Link.
Started with S3W-31079 on 26 Jan 2010; latest 10 Mar 2010. Each later question says it follows up an earlier answer.
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Executive what current or proposed rail projects have a higher benefit cost ratio than the Glasgow Airport Rail Link.
Stewart Stevenson, 4 Feb 2010: The current and proposed rail projects with a higher benefit cost ratio than the Glasgow Rail Link are: the Edinburgh to Glasgow Improvements Programme: Airdrie to Bathgate; Borders, and Edinburgh Trams. -
Whether the projects mentioned were compared on a like-for-like basis over the same time period; whether there was a common (a) discount and (b) inflation rate, and what account was taken of the complementary investment at Glasgow Airport of a new public transport interchange.
Stewart Stevenson, 20 Mar 2010: All infrastructure projects assessed by Transport Scotland are conducted in line with Scottish Transport Appraisal Guidance (STAG). This ensures consistency across projects as the same methodology is used to identify measure and record all costs, benefits and wider impacts. STAG recommends all costs and benefits are e… -
What the basis is of the assertion that the projects listed had a higher benefit cost ratio than the Glasgow Airport Rail Link (GARL), given that the published figures are GARL, 1.28, Borders, 1.36, Edinburgh to Glasgow Improvements Programme, 1.10, Airdrie to Bathgate, 1.81, Edinburgh Trams 1, 1.21, and Edinburgh Trams 2, 1.40.
Stewart Stevenson, 24 Mar 2010: The business case for all major transport projects is reviewed and updated on a regular basis as more information becomes available on costs, benefits and the wider impacts considered within the Scottish Transport Appraisal Guidance. This helps improve the robustness of forecasts and ensure projects continue to offer …
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.