Parliament Workbench

Question thread · 4 questions

What research was carried out on the economic impact of the Inverness bypass between July 2008 and the publication of the Strategic Transport Projects Review in December 2008 and what detailed results are available.

Started with S3W-21032 on 16 Feb 2009; latest 2 Apr 2009. Each later question says it follows up an earlier answer.

Follow-ups
3
longest chain 2 steps
Span
45 days
16 Feb 2009 to 2 Apr 2009
Answered
4 of 4
by Stewart Stevenson
Asked by
1
John Farquhar Munro

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S3W-21032 16 Feb 2009 John Farquhar Munro LD Answered

    To ask the Scottish Executive what research was carried out on the economic impact of the Inverness bypass between July 2008 and the publication of the Strategic Transport Projects Review in December 2008 and what detailed results are available.

    Stewart Stevenson, 11 Mar 2009: Economic output from the completion of the modelling of the operation of the Inverness bypass provided a benefit to cost ratio of less than 0.75 for the scheme in the period July 2008 to December 2008. This is reported in the option summary table (Annex 3, E6) of Report 3 to the STPR which can be found on the Transpor…
  2. S3W-21883 12 Mar 2009 John Farquhar Munro LD Answered

    Whether it will publish the detailed results of the modelling work on the Inverness bypass undertaken by Transport Scotland between July and December 2008 and the specific results on the costs and benefits of the project in real terms.

    Stewart Stevenson, 27 Mar 2009: The recommendations of the Strategic Transport Projects Review (STPR) are based on the most robust analysis and evidence available taking the future needs of Scotland''s strategic transport infrastructure into account. The results of the modelling work on the Inverness bypass are presented in the option summary table …
  3. S3W-22640 2 Apr 2009 John Farquhar Munro LD Answered

    On what date indicative estimates of the capital cost, value of cost to government and present value benefits were first arrived at in relation to the Inverness bypass.

    Stewart Stevenson, 7 May 2009: In relation to the Inverness bypass, the indicative estimates of the capital cost/value of cost to government and present value of benefits were first arrived at during May 2008 and between July and August 2008 respectively.
  4. S3W-22641 2 Apr 2009 John Farquhar Munro LD Answered follows S3W-21883

    Whether it will outline how indicative estimates of the value of cost to government and the present value benefits were arrived at in relation to the Inverness bypass.

    Stewart Stevenson, 5 May 2009: In relation to the Inverness bypass, the indicative estimate of the value of cost to government was arrived at based on the cost of similar recently implemented interventions discounted to present values in line with standard transport appraisal. The indicative estimate of the present value of benefits was arrived at …

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.

All question threads