Further to the answer to question S3W-21883 by Stewart Stevenson on 2 April 2009, on what date indicative estimates of the capital cost, va…

Answered Asked by John Farquhar Munro LD Lodged 2 Apr 2009

The question

To ask the Scottish Executive, further to the answer to question S3W-21883 by Stewart Stevenson on 2 April 2009, on what date indicative estimates of the capital cost, value of cost to government and present value benefits were first arrived at in relation to the Inverness bypass.

The answer

Answered by Stewart Stevenson on 7 May 2009 · 35 days after it was lodged, 2 days after it was due

In relation to the Inverness bypass, the indicative estimates of the capital cost/value of cost to government and present value of benefits were first arrived at during May 2008 and between July and August 2008 respectively.