Question thread · 4 questions
Which IT projects it has initiated and started without an estimate of costs having been established in advance.
Started with S2W-27685 on 4 Aug 2006; latest 12 Sep 2006. Each later question says it follows up an earlier answer.
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Executive which IT projects it has initiated and started without an estimate of costs having been established in advance.
Tom McCabe, 7 Sep 2006: All internal IT projects thatrequire funding are subject to approval by the Executive’s Information Systems SteeringGroup (SEISSG), or by the ICT Senior Managers to whom authority to approve fundingfor smaller projects is delegated. All internal IT projects are managed in accordancewith Prince 2 Project Management met… -
Why no budget was set for the criminal history system replacement project, given that it followed the Prince methodology.
Cathy Jamieson, 26 Sep 2006: At that time the CriminalHistory System Replacement Project Board was responsible for the management of the Criminal History Replacement Project under the oversight of the ScottishPolice Information Strategy (SPIS) Programme Board. -
Who made the decision that the criminal history system replacement project could proceed beyond the planning stage without a budget being set.
Cathy Jamieson, 26 Sep 2006: I refer the member to the answerto question S2W-28313 on 26 September 2006. All answers to written parliamentaryquestions are available on the Parliaments website, the search facility forwhich can be found at: http://www.scottish.parliament.uk/webapp/wa.search. -
What additional controls and reporting mechanisms were put in place to compensate for the lack of a designated budget against which to monitor project spending in respect of the criminal history system replacement project.
Cathy Jamieson, 26 Sep 2006: When the Scottish Executivebecame aware that the replacement system would not be delivered by March 2004 anumber of steps were taken to improve management of the project. Firstly, Scottish Police InformationStrategy (SPIS) was brought within the governance arrangements that were put inplace by the establishment of the…
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.