What the cost to it has been of monitoring private finance initiative contracts in each of the last five years.

Started with S1W-28226 on 5 Aug 2002; latest 18 Oct 2002. Each later question says it follows up an earlier answer.

Follow-ups
4
longest chain 2 steps
Span
74 days
5 Aug 2002 to 18 Oct 2002
Answered
5 of 5
by Andy Kerr
Asked by
1
Roseanna Cunningham

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S1W-28226 5 Aug 2002 Roseanna Cunningham SNP Answered

    To ask the Scottish Executive what the cost to it has been of monitoring private finance initiative contracts in each of the last five years.

    Andy Kerr, 9 Sep 2002: The information requested is contained in the following table for the three Scottish Executive private finance initiative contracts. It is the responsibility of other public authorities to monitor their own private finance initiative contracts. The figures include the costs of technical and professional supervision an…
  2. S1W-29432 17 Sep 2002 Roseanna Cunningham SNP Answered

    What evidence it has to support the statement that, in comparison with private finance initiative contracts, "broadly equivalent costs are incurred in relation to professional fees for the preparation, construction and operation of conventionally funded projects", giving specific examples of such projects where this is the case.

    Andy Kerr, 30 Sep 2002: The statement referred to relates to the costs of monitoring contracts. All contracts have to be monitored whether they are PPP contracts or conventional contracts. There are sound reasons for doing this, not least to ensure propriety and value for money. There is a cost attached to this. It is not possible to provide…
  3. S1W-30804 18 Oct 2002 Roseanna Cunningham SNP Answered

    What precisely is meant by "broadly equivalent costs".

    Andy Kerr, 12 Nov 2002: As I previously stated in the answer to question S1W-29432, it is not possible to provide specific examples as contract monitoring costs are not separately identified in conventional contracts.
  4. S1W-30805 18 Oct 2002 Roseanna Cunningham SNP Answered follows S1W-29432

    Whether it will detail each type of cost incurred in monitoring contracts for the operation of conventionally funded capital projects.

    Andy Kerr, 12 Nov 2002: For trunk roads, monitoring of capital conventional construction contracts includes: checks of contractors design proposals; checking contractors construction proposals; monitoring compliance of construction activities in relation to contract requirements; testing the quality of materials and workmanship employed in c…
  5. S1W-30806 18 Oct 2002 Roseanna Cunningham SNP Answered follows S1W-29432

    What information it has on the costs of monitoring contracts for the operation of conventionally funded capital projects.

    Andy Kerr, 12 Nov 2002: For trunk roads, fees are paid to Consulting Engineers or Agent Authorities for the supervision of construction contracts conventionally procured and for major schemes. Records are held against individual contracts and aggregated to provide annual totals across the portfolio.

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.