Written Question · S1W-28226 · Session 1

What the cost to it has been of monitoring private finance initiative contracts in each of the last five years.

Answered Asked by Roseanna Cunningham SNP Lodged 5 Aug 2002

The question

To ask the Scottish Executive what the cost to it has been of monitoring private finance initiative contracts in each of the last five years.

The answer

Answered by Andy Kerr on 9 Sep 2002 · 35 days after it was lodged, 7 days after it was due

The information requested is contained in the following table for the three Scottish Executive private finance initiative contracts. It is the responsibility of other public authorities to monitor their own private finance initiative contracts. The figures include the costs of technical and professional supervision and non-technical monitoring of contractual performance and penalty clauses. They include an estimate of staff time involved. Payments cover the monitoring of construction of new works as well as operation and maintenance. The cost of monitoring contracts during construction would occur whether the contract was under conventional procurement or the private finance initiative. These respective costs are evaluated before the PPP commences and the PPP has to demonstrate better value for money.Broadly equivalent costs are incurred in relation to professional fees for the preparation, construction and operation of conventionally-funded projects. | Skye Bridge | M6 DBFO | Kilmarnock Prison
1997-98 | 74,359 | 1,219,547 | Nil
1998-99 | 45,403 | 1,108,260 | Nil
1999-2000 | 32,156 | 1,073,500 | 240,000
2000-01 | 39,357 | 341,472 | 230,000
2001-02 | 11,019 | 200,000 | 240,000
Note:1. The figures for 2001-02 for the Skye Bridge and M6 DBFO are lower than the previous four years because the previous four years include costs related to monitoring the construction phase.