Whether it will list all ancillary activities to the Holyrood Parliament Building that are being funded by other public bodies, including landscaping and road realignment, and the costs of each of these activities.
Started with S1W-06090 on 6 Apr 2000; latest 11 Jul 2000. Each later question says it follows up an earlier answer.
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Executive whether it will list all ancillary activities to the Holyrood Parliament Building that are being funded by other public bodies, including landscaping and road realignment, and the costs of each of these activities.
Jack McConnell, 28 Apr 2000: The Scottish Executive intends to fund landscaping and road activities adjacent to the Holyrood Parliament building site, and this work will mainly be undertaken through Historic Scotland. Firm cost estimates for these activities are not yet available, and will be determined in the light of finalisation of the Holyroo… -
When it expects to be able to publish firm cost estimates with regard to any or all of the ancillary works associated with the Holyrood Project and whether road realignment and landscaping costs are likely to be around #13,000,000.
Jack McConnell, 16 May 2000: Firm cost estimates for these works are not yet available and can only be produced after the Holyrood design and external works proposals have been finalised. -
And in the light of the finalisation of the Holyrood design, what roadworks will need to take place as a result of the location of the new Parliament building at Holyrood; how much such roadworks are expected to cost and how much the landscaping of the surrounding area is expected to cost.
Jack McConnell, 20 Jul 2000: External works proposals are not yet finalised, and firm cost estimates are therefore not available. £2.5 million has been made available to Historic Scotland for works in Holyrood Park likely to be required this year. In addition, the Scottish Executive Development Department has been discussing with Edinburgh City C… -
Whether it can now give a date when cost estimates will be available for ancillary works associated with the Holyrood Project.
Jack McConnell, 21 Aug 2000: It is not yet possible to provide a firm date when cost estimates for ancillary works associated with the Holyrood Project will be available. This is dependent on further development of detailed design of the work and its programming.
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.