Written Question · S1W-06451 · Session 1
Further to the answer to question S1W-6090 by Mr Jack McConnell on 28 April 2000, when it expects to be able to publish firm cost estimates…
The question
To ask the Scottish Executive, further to the answer to question S1W-6090 by Mr Jack McConnell on 28 April 2000, when it expects to be able to publish firm cost estimates with regard to any or all of the ancillary works associated with the Holyrood Project and whether road realignment and landscaping costs are likely to be around #13,000,000.
The answer
Firm cost estimates for these works are not yet available and can only be produced after the Holyrood design and external works proposals have been finalised.
In the Official Report
No contribution in the Official Report cites S1W-06451 by reference.