Parliament Workbench

Question thread · 2 questions

Whether further preliminary work is required on the Borders Railway project and, if so, whether this will involve additional costs.

Started with S4W-02836 on 19 Sep 2011; latest 5 Oct 2011. Each later question says it follows up an earlier answer.

Follow-ups
1
longest chain 1 step
Span
16 days
19 Sep 2011 to 5 Oct 2011
Answered
2 of 2
by Keith Brown
Asked by
1
Lewis Macdonald

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S4W-02836 19 Sep 2011 Lewis Macdonald Lab Answered

    To ask the Scottish Executive whether further preliminary work is required on the Borders Railway project and, if so, whether this will involve additional costs.

    Keith Brown, 29 Sep 2011: Further preliminary work is scheduled for the Borders Railway, as would be expected on a large scale, complex project and the costs have been accounted for in the overall project capital budget.
  2. S4W-03191 5 Oct 2011 Lewis Macdonald Lab Answered

    What preliminary works are scheduled for the Borders Railway project and when these are expected to be completed.

    Keith Brown, 27 Oct 2011: The package of advance utility diversion works which commenced in March 2010 is nearing completion. Transport Scotland is currently in discussions with Network Rail regarding additional preliminary works which may be required in advance of main construction works.

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.

All question threads