Written Question · S4W-03191 · Session 4
Further to the answer to question S4W-02836 by Keith Brown on 29 September 2011, what preliminary works are scheduled for the Borders Railw…
The question
To ask the Scottish Executive, further to the answer to question S4W-02836 by Keith Brown on 29 September 2011, what preliminary works are scheduled for the Borders Railway project and when these are expected to be completed.
The answer
The package of advance utility diversion works which commenced in March 2010 is nearing completion. Transport Scotland is currently in discussions with Network Rail regarding additional preliminary works which may be required in advance of main construction works.
In the Official Report
No contribution in the Official Report cites S4W-03191 by reference.