Further to the answer to question S6W-15780 by Lorna Slater on 22 March 2023, what its position is on conclusion 7 of the report, Stop, Sor…
The question
To ask the Scottish Government, further to the answer to question S6W-15780 by Lorna Slater on 22 March 2023, what its position is on conclusion 7 of the report, Stop, Sort, Burn, Bury? Independent Review of the Role of Incineration in the Waste Hierarchy in Scotland, that “Scotland should not construct more capacity than it needs and only some of the currently planned capacity should be built”, and, if it accepts this conclusion, what its position is on whether ascertaining which of those planned developments should be built can only be determined based on the forthcoming capacity cap, which may indicate a lower capacity than is currently in development.
The answer
The first report of the independent review of incineration conducted a capacity analysis. It recommended that the Scottish Government ensure no further planning permission (i.e. beyond that already in place) is granted to incineration infrastructure within the scope of the Review, unless balanced by an equal or greater closure of capacity, subject to certain limited exceptions. Our response to the Review set out our intentions to set out in National Planning Policy that the Scottish Government does not support the development of further municipal waste incineration capacity in Scotland, with very limited exceptions. Following the adoption and publication of National Planning Framework 4 on 13 February 2023 that action is now complete.
To support future planning decisions, we accepted the review’s separate recommendation to develop an indicative capacity cap. However, it is important that any indicative cap is as robust as possible and developing such a cap will be a significant piece of work.
Where relevant consents and permissions have already been granted, the review noted that it is ‘unlikely that all facilities in the pipeline will be built, especially those that have not yet secured full financial backing’. The Review did suggest some principles, based on stakeholder feedback, that might be applied to determine which of the pipeline facilities would be best to build and which might be deprioritised, in light of the potential overcapacity predicted. These included:Proper appreciation of resource and waste management as a complex and interdependent system.Application of the proximity principle (that waste should generally be managed as near as possible to its place of production) at a sub-national level.Consideration of access to low-carbon transport, especially where longer distances are involved.Opportunities for synergy with other activities. For incineration, this should prioritise access to heat offtake and, in due course, carbon dioxide offtake options.Local environmental and social impacts.Wider environmental impacts, such as the carbon and other benefits from recycling to avoid virgin raw material production.
We would encourage those involved in the development of these facilities to take into account capacity and the principles set out by the independent review of incineration.
To support future planning decisions, we accepted the review’s separate recommendation to develop an indicative capacity cap. However, it is important that any indicative cap is as robust as possible and developing such a cap will be a significant piece of work.
Where relevant consents and permissions have already been granted, the review noted that it is ‘unlikely that all facilities in the pipeline will be built, especially those that have not yet secured full financial backing’. The Review did suggest some principles, based on stakeholder feedback, that might be applied to determine which of the pipeline facilities would be best to build and which might be deprioritised, in light of the potential overcapacity predicted. These included:Proper appreciation of resource and waste management as a complex and interdependent system.Application of the proximity principle (that waste should generally be managed as near as possible to its place of production) at a sub-national level.Consideration of access to low-carbon transport, especially where longer distances are involved.Opportunities for synergy with other activities. For incineration, this should prioritise access to heat offtake and, in due course, carbon dioxide offtake options.Local environmental and social impacts.Wider environmental impacts, such as the carbon and other benefits from recycling to avoid virgin raw material production.
We would encourage those involved in the development of these facilities to take into account capacity and the principles set out by the independent review of incineration.
In the Official Report