What steps it can take to ensure that SEPA issues no new waste management licences for incineration until work has been completed to develo…

Answered Asked by Maurice Golden Con Lodged 8 Mar 2023

The question

To ask the Scottish Government what steps it can take to ensure that SEPA issues no new waste management licences for incineration until work has been completed to develop an indicative cap on residual waste treatment capacity, as outlined in recommendation 5 of the report, Stop, Sort, Burn, Bury? Independent Review of the Role of Incineration in the Waste Hierarchy in Scotland.

The answer

Answered by Lorna Slater on 22 Mar 2023 · 14 days after it was lodged, on time

The independent review of the role of incineration in Scotland’s waste hierarchy made it clear that Scotland does not need additional municipal waste incineration facilities to treat our unavoidable and unrecyclable municipal residual waste, beyond those for which planning permission has already been granted, with very limited exceptions.
That is why we introduced restrictions on energy from waste developments in National Planning Framework 4 (NPF4), which came into effect on 13 February 2023. This sets out that development proposals for energy from waste facilities will not be supported except in limited circumstances where a national or local need has been sufficiently demonstrated (e.g. in terms of capacity need or carbon benefits) as part of a strategic approach to residual waste management.
SEPA cannot issue a Pollution Prevention and Control (PPC) permit in respect of a waste incineration facility in the absence of planning permission. Introduction of restrictions on developments in NPF4, therefore, also prevent PPC permits being issued for new facilities in line with recommendation 4 of the incineration review, which noted that the Scottish Government should ensure that no further planning permission (i.e. beyond that already in place) is granted to incineration infrastructure within the scope of the Review unless balanced by an equal or greater closure of capacity, with very limited exceptions.

In the Official Report

No contribution in the Official Report cites S6W-15780 by reference.