Further to the answer to question S6W-02823 by Kate Forbes on 24 September 2021, how much of the "up to £10 million" that was committed to …

Answered Asked by Liam Kerr Con Lodged 19 Apr 2022

The question

To ask the Scottish Government, further to the answer to question S6W-02823 by Kate Forbes on 24 September 2021, how much of the "up to £10 million" that was committed to help extend digital infrastructure across the City Deal region and the City Network Extension project has been spent; what precisely has been achieved with this funding; what precisely it projects will be delivered from the remaining funding, and, in light of the Aberdeen project being "expected to complete later" in 2021, whether it did so, and whether the Full Fibre Project in Aberdeenshire that is expected to complete in 2022 will do so.

The answer

Answered by Kate Forbes on 28 Apr 2022 · 9 days after it was lodged, on time

The Memorandum of Understanding for additional investment in the Aberdeen City Region allows for up to £10 million of funding to help extend digital infrastructure across the region. To date £5 million of this funding has been spent.
£2 million was invested in the City Network Extension project which connected 57 council sites to full fibre with build completing in 2021. This investment successfully stimulated around £40 million of commercial investment across the region by CityFibre and Vodafone who are utilising this infrastructure to help extend the reach of full fibre broadband across the region. In January 2022 CityFibre announced a further £19 million of investment in Aberdeen.
£3 million was invested in the Full Fibre Infrastructure project which will connect 192 public sector and NHS sites across Aberdeenshire. To date, 190 sites have been connected with one site expected to be completed in the coming months, and the final site – an additional site made possible by cost savings – to be connected once construction is completed in summer 2023.
We continue to work closely with the Aberdeen City Region Deal team as they develop options for the remaining funding.