Written Question · S6W-02823 · Session 6
Which additional projects will be funded from the £254 million to support transport, housing and digital initiatives announced in 2016 as p…
The question
To ask the Scottish Government which additional projects will be funded from the £254 million to support transport, housing and digital initiatives announced in 2016 as part of the Aberdeen City Region Deal.
The answer
In 2016 the Scottish Government committed to invest up to £125 million in the Aberdeen City Region Deal, matched by the UK Government. Alongside the Deal, the Scottish Government announced an additional £254 million of investment in the North East’s Infrastructure.
This includes £200 million to help improve journey times and increase capacity on key rail links between Aberdeen and the Central Belt, and £24m for a new grade separated junction at the Laurencekirk A90/A937 south junction. The rail improvement project is on course to conclude option selection by early next year and we expect to complete the project by the end of 2026. We also continue to push forward with the statutory authorisation stage for the A90/A937 Laurencekirk Junction Improvement scheme. Delivery of the scheme itself can only commence if it is approved under the relevant statutory procedures, at which point a timetable for the construction phase can be set.
In addition, up to £10 million was committed to help extend digital infrastructure across the City Deal region and the City Network Extension project, which is delivering full fibre connectivity to a number of public sector sites across the city of Aberdeen, is expected to complete later this year while the Full Fibre Project in Aberdeenshire is expected to complete next year.
To date no eligible housing infrastructure projects have been submitted as part of the £20m indicative allocation referred to in the 2016 agreement.
This includes £200 million to help improve journey times and increase capacity on key rail links between Aberdeen and the Central Belt, and £24m for a new grade separated junction at the Laurencekirk A90/A937 south junction. The rail improvement project is on course to conclude option selection by early next year and we expect to complete the project by the end of 2026. We also continue to push forward with the statutory authorisation stage for the A90/A937 Laurencekirk Junction Improvement scheme. Delivery of the scheme itself can only commence if it is approved under the relevant statutory procedures, at which point a timetable for the construction phase can be set.
In addition, up to £10 million was committed to help extend digital infrastructure across the City Deal region and the City Network Extension project, which is delivering full fibre connectivity to a number of public sector sites across the city of Aberdeen, is expected to complete later this year while the Full Fibre Project in Aberdeenshire is expected to complete next year.
To date no eligible housing infrastructure projects have been submitted as part of the £20m indicative allocation referred to in the 2016 agreement.