Parliament Workbench
Data: Motions & questions to 3 Dec 2026

Written Question · S5W-30721 · Session 5

Further to the answer to question S5W-29800 by Jean Freeman on 10 July 2020, whether construction commenced in June 2020 and, if so, what f…

Answered Asked by Edward Mountain Con Lodged 15 Jul 2020

The question

To ask the Scottish Government, further to the answer to question S5W-29800 by Jean Freeman on 10 July 2020, whether construction commenced in June 2020 and, if so, what form this took.

The answer

Answered by Jeane Freeman on 31 Jul 2020 · 16 days after it was lodged, on time

Due to the impact of the COVID-19 pandemic, construction commenced on the North of Scotland Elective Care Centre on 20 July 2020. This consists of advanced construction site works, including archaeological examinations.
It is anticipated that the main contract construction work will start in mid-October 2020.

In the Official Report

No contribution in the Official Report cites S5W-30721 by reference.