Written Question · S5W-29800 · Session 5
When it was last given an update from NHS Highland regarding the development of the North of Scotland Elective Care Centre.
The question
To ask the Scottish Government when it was last given an update from NHS Highland regarding the development of the North of Scotland Elective Care Centre.
The answer
The National Elective Centre Programme received a report update on 2 nd June regarding the NHS Highland Elective Centre Project. This followed a discussion with the NHS Highland Elective Centre Senior Responsible Owner on 28 th May and a follow-up discussion took place on Monday 15 th June.
The National Elective Centre Programme is regularly updated on the development of the North of Scotland Elective Care Centre.
Construction is due to commence in June 2020 with a Construction Completion Date of August 2022.
The National Elective Centre Programme is regularly updated on the development of the North of Scotland Elective Care Centre.
Construction is due to commence in June 2020 with a Construction Completion Date of August 2022.
In the Official Report
No contribution in the Official Report cites S5W-29800 by reference.