Further to the answer to question S5W-20623 by Michael Matheson on 10 January 2019, on what date the impact study was completed; what subse…
The question
To ask the Scottish Government, further to the answer to question S5W-20623 by Michael Matheson on 10 January 2019, on what date the impact study was completed; what subsequent work was carried out to update these figures to reflect changes in economic circumstances, and when this was completed.
The answer
The Economic Activity and Location Impact study was published in 2008. Investments such as the AWPR/B-T project are vitally important to the regional economy which has been impacted in recent years from the challenges facing the oil and gas industry.
While no further work of this nature has been carried out specifically for this project, the rise in the oil price from 2016, coupled with restructuring in the North Sea industry, has provided a boost to confidence and activity in the sector which we would expect to have a more positive impact on the regional and national economy. In addition, economic performance in the north east has been relatively strong recently with employment, economic activity rate and output per head all above Scottish average showing recovery since oil price drop.
Once the AWPR B/T project is fully open to traffic Transport Scotland will progress a formal evaluation of the project, in line with Scottish Trunk Road Infrastructure Project Evaluation (STRIPE) Guidance. The evaluation will be carried out to assess the impact of the scheme by comparing conditions after opening with forecasts made during scheme design and development.
The main areas evaluated will include: scheme objectives; operation; environment; safety; economy; integration; accessibility and social inclusion; and cost to government. Transport Scotland closely monitors the results of evaluation to learn lessons and ensure that there is a continuous improvement in the design and development of roads projects. Once completed, STRIPE Evaluation reports are published on Transport Scotland’s website.
While no further work of this nature has been carried out specifically for this project, the rise in the oil price from 2016, coupled with restructuring in the North Sea industry, has provided a boost to confidence and activity in the sector which we would expect to have a more positive impact on the regional and national economy. In addition, economic performance in the north east has been relatively strong recently with employment, economic activity rate and output per head all above Scottish average showing recovery since oil price drop.
Once the AWPR B/T project is fully open to traffic Transport Scotland will progress a formal evaluation of the project, in line with Scottish Trunk Road Infrastructure Project Evaluation (STRIPE) Guidance. The evaluation will be carried out to assess the impact of the scheme by comparing conditions after opening with forecasts made during scheme design and development.
The main areas evaluated will include: scheme objectives; operation; environment; safety; economy; integration; accessibility and social inclusion; and cost to government. Transport Scotland closely monitors the results of evaluation to learn lessons and ensure that there is a continuous improvement in the design and development of roads projects. Once completed, STRIPE Evaluation reports are published on Transport Scotland’s website.
In the Official Report