Further to the statement by the transport secretary on the Transport Scotland website that the Aberdeen Western Peripheral Route (AWPR) wil…

Answered Asked by Tom Mason Con Lodged 14 Dec 2018

The question

To ask the Scottish Government, further to the statement by the transport secretary on the Transport Scotland website that the Aberdeen Western Peripheral Route (AWPR) will unlock £6 billion for the north east economy and create 14,000 jobs over a 30-year period, what research it has undertaken on this; how these figures were calculated, and what methodology it used in making the calculations.

The answer

Answered by Michael Matheson on 10 Jan 2019 · 27 days after it was lodged, on time

The estimates of future economic and employment benefits that would arise from the opening of the AWPR are taken from the findings of an Economic Activity and Location Impact study carried out by economists when proposals were being developed for the project.
The study methodology involved a combination of desk research, consultations and face to face surveys with sample businesses throughout the study area. This information was used to provide estimates of the additional income and employment which would be created for identified market sectors. The calculations for these estimates took account of: the value of sales and costs in the study area economy for each identified market sector; the level of sales required to support each job in each market sector; the average change in sales and costs across sampled businesses within each sector; the increase in employment associated with the increase in sales; the expected timing of the realisation of benefits following opening of the AWPR; and the total value of the increased income to the study area over a 30 year assessment period.

In the Official Report

No contribution in the Official Report cites S5W-20623 by reference.