Written Question · S4W-00236 · Session 4

Further to the answer to question S3W-39333 by Keith Brown on 24 February 2011, whether there will be changes to the (a) final cost or (b) …

Answered Asked by Lewis Macdonald Lab Lodged 25 May 2011

The question

To ask the Scottish Executive, further to the answer to question S3W-39333 by Keith Brown on 24 February 2011, whether there will be changes to the (a) final cost or (b) completion date of the (i) Forth Replacement Crossing, (ii) M74 extension, (iii) M8/Network Improvements/M74 Raith, (iv) M80 Completion (Stepps to Haggs), (v) Aberdeen Western Peripheral Route or (vi) Borders Railway project in the current parliamentary session.

The answer

Answered by Keith Brown on 7 Jun 2011 · 13 days after it was lodged, on time

The total out-turn cost of the Forth Replacement Crossing is now £1.62 billion with an estimated completion date of 2016-17.
All other information contained in the answer to question S3W-39333 remains the same.