Written Question · S3W-39333 · Session 3
Further to the answer to question S3W-32043 by Stewart Stevenson on 11 March 2010, what the most up-to-date estimate is of the (a) final co…
The question
To ask the Scottish Executive, further to the answer to question S3W-32043 by Stewart Stevenson on 11 March 2010, what the most up-to-date estimate is of the (a) final cost and (b) completion date of the (i) Forth Replacement Crossing, (ii) M74 extension, (iii) M8 completion, (iv) M80 completion, (v) Aberdeen Western Peripheral Route and (vi) Borders Railway project.
The answer
The most up to date estimates are shown in the following table:
Project
| (a) Estimated Final Cost
| (b) Estimated Completion Date
(i) Forth Replacement Crossing
| £1.7 billion to £2.3billion
| 2016-17
(ii) M74 Extension
| £692 million
| June 2011
(iii) M8/Network Improvements/ M74 Raith
| £320 million
| Operational by 2016-17 (detailed timetable subject to review)
(iv) M80 Completion (Stepps to Haggs)
| £320 million
| Autumn 2011
(v) Aberdeen Western Peripheral Route
| £295 million to £395 million. To be reviewed and updated once the legal challenges submitted to the Court of Session have been resolved.
| To be reviewed once the legal challenges submitted to the Court of Session have been resolved. Assuming a successful outcome to the challenges, a thorough review of the remaining stages of the project will be undertaken to produce a definitive timetable to construction.
(vi) Borders Railway (formerly known as the Waverley Railway Project)
| £235 million to £295 million (at 2012 prices)
| 2014
Project
| (a) Estimated Final Cost
| (b) Estimated Completion Date
(i) Forth Replacement Crossing
| £1.7 billion to £2.3billion
| 2016-17
(ii) M74 Extension
| £692 million
| June 2011
(iii) M8/Network Improvements/ M74 Raith
| £320 million
| Operational by 2016-17 (detailed timetable subject to review)
(iv) M80 Completion (Stepps to Haggs)
| £320 million
| Autumn 2011
(v) Aberdeen Western Peripheral Route
| £295 million to £395 million. To be reviewed and updated once the legal challenges submitted to the Court of Session have been resolved.
| To be reviewed once the legal challenges submitted to the Court of Session have been resolved. Assuming a successful outcome to the challenges, a thorough review of the remaining stages of the project will be undertaken to produce a definitive timetable to construction.
(vi) Borders Railway (formerly known as the Waverley Railway Project)
| £235 million to £295 million (at 2012 prices)
| 2014