Further to the answer to question S3W-27650 by Stewart Stevenson on 8 October 2009, what the most up-to-date estimate is of the (a) final c…

Answered Asked by Jamie McGrigor Con Lodged 1 Mar 2010

The question

To ask the Scottish Executive, further to the answer to question S3W-27650 by Stewart Stevenson on 8 October 2009, what the most up-to-date estimate is of the (a) final cost and (b) completion date of the (i) Airdrie Bathgate Rail Link Project, (ii) Waverley Railway Project, (iii) Edinburgh Trams Project, (iv) Forth Replacement Crossing, (v) M74 extension, (vi) M8 Baillieston to Newhouse, (vii) M80 Stepps to Haggs upgrade and (viii) Aberdeen Western Peripheral Route.

The answer

Answered by Stewart Stevenson on 11 Mar 2010 · 10 days after it was lodged, on time

The most up to date estimates are shown in the following table:
a. Project
| (a) estimated final cost
| (b) estimated completion date

(i) Airdrie Bathgate Rail Link Project
| £375m
| December 2010

(ii) Borders Railway (formerly known as the Waverley Railway Project)
| £235m
- £295m (at 2012 prices)
| 2014

(iii) Edinburgh Trams project
| £533m
| January 2013

(iv) Forth Replacement Crossing
| £1.7bn
- £2.3bn
| 2016
- 17

(v) M74 Extension
| £692m
| August 2011

(vi) M8 Baillieston “ Newhouse
| £170m
- £210m
| 2013 “ 14

(vii) M80 Completion (Stepps to Haggs)
| £320m
| September 2011

(viii) Aberdeen Western Peripheral Route
| £295m
- £395m
| Subject to completing the necessary statutory procedures it is expected construction will commence in 2011. Assuming Parliamentary approval is given, a review of the remaining stages of the project will be undertaken to produce a definitive completion timetable.