Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S3W-39861 · Session 3

Further to the answer to question S3W-39416 by Keith Brown on 23 February 2011, whether the indicative timetable for the delivery of the ne…

Answered Asked by John Wilson SNP Lodged 24 Feb 2011

The question

To ask the Scottish Executive, further to the answer to question S3W-39416 by Keith Brown on 23 February 2011, whether the indicative timetable for the delivery of the new class 380 trains remains confidential and, if so, for what reason.

The answer

Answered by Keith Brown on 9 Mar 2011 · 13 days after it was lodged, on time

The timetable for the delivery of the new class 380 trains is not confidential. ScotRail anticipates delivery of the full fleet of class 380 trains by June 2011.

In the Official Report

No contribution in the Official Report cites S3W-39861 by reference.