The question

To ask the Scottish Executive, further to the answer to question S3W-38973 by Keith Brown on 3 February 2011, whether ScotRail has given a timetable for delivery of new Class 380 trains by Siemens.

The answer

Answered by Keith Brown on 23 Feb 2011 · 20 days after it was lodged, on time

Yes, the Scottish Executive has received an indicative timetable for the delivery of the new class 380 trains. This is subject to ongoing discussion between ScotRail and the train manufacturer Siemens.