The question

To ask the Scottish Executive what agreement was reached with ScotRail regarding the timetable for trains on the Airdrie-Bathgate line.

The answer

Answered by Keith Brown on 3 Feb 2011 · 10 days after it was lodged, on time

A service level commitment for new Airdrie-Bathgate services was finalised with ScotRail in December 2009. This reflects the four trains per hour assumption in the business case for Airdrie-Bathgate services. However, a revised introductory hourly timetable was agreed with ScotRail to commence from December 2010 as less rolling stock was available than planned due to delays in the delivery of the new Class 380 trains by Siemens.