The question
To ask the Scottish Executive, further to the answer to question S3W-18978 by Stewart Stevenson on 14 January 2009 and the commitment made by the First Minister in The Press and Journal on 18 December 2008 that “It will not be (down to) Aberdeen city. It will be the Scottish Government that will do the work and then it will be handed over as an improved roundabout”, when work at the junction of the A90 and A96 trunk roads is expected to (a) begin and (b) be completed.
The answer
I refer the member to the answer to question S3W-19898 on 6 February 2009. All answers to written parliamentary questions are available on the Parliament''s website, the search facility for which can be found at http://www.scottish.parliament.uk/Apps2/Business/PQA/Default.aspx.