Whether it intends to detrunk the A90 in the City of Aberdeen on completion of the Aberdeen Western Peripheral Route and, if so, whether it…

Answered Asked by Lewis Macdonald Lab Lodged 12 Dec 2008

The question

To ask the Scottish Executive whether it intends to detrunk the A90 in the City of Aberdeen on completion of the Aberdeen Western Peripheral Route and, if so, whether it intends to do so immediately following the opening of the new trunk road.

The answer

Answered by Stewart Stevenson on 14 Jan 2009 · 33 days after it was lodged, on time

The existing A90 between Charleston and Blackdog will be de-trunked on 1 April after the date on which the new special roads and trunk roads of the Aberdeen Western Peripheral Route are all open.

In the Official Report

No contribution in the Official Report cites S3W-18978 by reference.