Written Question · S3W-16183 · Session 3
Further to the answer to question S3W-15716 by Stewart Stevenson on 10 September 2008, what investment is being made and action taken to en…
The question
To ask the Scottish Executive, further to the answer to question S3W-15716 by Stewart Stevenson on 10 September 2008, what investment is being made and action taken to ensure that there is no repeat of the flooding incident that took place between Waverley and Haymarket stations during summer 2008.
The answer
The recent flooding in Princes Street Gardens was due to a severe downpour. The volume of water was overwhelming and the drainage systems (both railway and local authority which the railway feeds into) could not cope. Network Rail is developing a scheme that will protect the railway from similar future downpours.
In the Official Report
No contribution in the Official Report cites S3W-16183 by reference.