Written Question · S3W-15716 · Session 3
How it will ensure that Network Rail is given sufficient resources, such as trackside pumps and drains, to cope with heavy or prolonged rai…
The question
To ask the Scottish Executive how it will ensure that Network Rail is given sufficient resources, such as trackside pumps and drains, to cope with heavy or prolonged rainfall so that normal train services can continue despite severe rainfall.
The answer
The Scottish ministers'' high level output specification (HLOS) was published in July 2007 and specified ministers'' requirements for the rail network from April 2009 to March 2014. The HLOS makes clear that Network Rail require to pursue continued improvements to operational and financial performance, including improved resilience. The public funding available to support the HLOS includes an appropriate element for the continued maintenance of the Scottish rail network.
In the Official Report
No contribution in the Official Report cites S3W-15716 by reference.