Written Question · S3W-02522 · Session 3

Further to the answer to question S3W-1811 by Stewart Stevenson on 24 July 2007, whether its cost estimate for the Aberdeen Western Periphe…

Answered Asked by Des McNulty Lab Lodged 27 Jul 2007

The question

To ask the Scottish Executive, further to the answer to question S3W-1811 by Stewart Stevenson on 24 July 2007, whether its cost estimate for the Aberdeen Western Peripheral Route is based on the current preferred option including the Stonehaven spur and how this estimate was reached.

The answer

Answered by Stewart Stevenson on 23 Aug 2007 · 27 days after it was lodged, on time

The current cost estimate,in the range £295 million to £395 million, is based on the Milltimber Brae optionand includes costs for the Stonehaven Fastlink. The cost estimate was prepared bythe project team in discussion with the Managing Agent and Consulting Engineersusing data benchmarked against similar Scottish schemes.