Written Question · S3W-01811 · Session 3
What the latest estimate is of the cost of the Aberdeen Western Peripheral Route and the benefit to cost ratio associated with the project.
The question
To ask the Scottish Executive what the latest estimate is of the cost of the Aberdeen Western Peripheral Route and the benefit to cost ratio associated with the project.
The answer
The cost estimate inheritedfrom the previous administration is in the range £295 million
- £395 million.This is based on the risks as currently identified but we will continue tomonitor this in light of prevailing tender prices for roads contracts. Thefinal costs will not be known until tenders have been returned and the contractcompleted. The benefit to cost ratio is approximately 5:1.
- £395 million.This is based on the risks as currently identified but we will continue tomonitor this in light of prevailing tender prices for roads contracts. Thefinal costs will not be known until tenders have been returned and the contractcompleted. The benefit to cost ratio is approximately 5:1.
In the Official Report
No contribution in the Official Report cites S3W-01811 by reference.