The question

To ask the Scottish Executive, further to the answer to question S3W-1811 by Stewart Stevenson on 24 July 2007, when the cost estimate from the Aberdeen Western Peripheral Route was first made.

The answer

Answered by Stewart Stevenson on 23 Aug 2007 · 27 days after it was lodged, on time

The £295 million to£395 million cost estimate for the Aberdeen Western Peripheral Route was first made prior to the announcement of the preferredroute choice in December 2005.