Written Question · S3W-02521 · Session 3
Further to the answer to question S3W-1811 by Stewart Stevenson on 24 July 2007, when the cost estimate from the Aberdeen Western Periphera…
The question
To ask the Scottish Executive, further to the answer to question S3W-1811 by Stewart Stevenson on 24 July 2007, when the cost estimate from the Aberdeen Western Peripheral Route was first made.
The answer
The £295 million to£395 million cost estimate for the Aberdeen Western Peripheral Route was first made prior to the announcement of the preferredroute choice in December 2005.
In the Official Report
No contribution in the Official Report cites S3W-02521 by reference.