Further to the answer to question S2W-23450 by Malcolm Chisholm on 9 March 2006, whether it understands it to be possible, under the propos…

Answered Asked by Murray Tosh Con Lodged 27 Mar 2006

The question

To ask the Scottish Executive, further to the answer to question S2W-23450 by Malcolm Chisholm on 9 March 2006, whether it understands it to be possible, under the proposals for planning gain supplement, for developers and/or landowners to be exempted from planning gain supplement in circumstances where planning obligations have been entered into under section 75 of the Town and Country Planning (Scotland) Act 1997 in order to provide funding for infrastructure which is the subject of an Act of the Scottish Parliament arising from a Private Bill.

The answer

Answered by Malcolm Chisholm on 20 Apr 2006 · 24 days after it was lodged, on time

The UK Government’s consultationpaper on a planning-gain supplement states that it is envisaged that planning obligationswould be factored into the planning value for any site. Any obligations enteredinto under section 75 would therefore be a prior charge and deducted from the calculationof planning gain supplement liability.

In the Official Report

No contribution in the Official Report cites S2W-24696 by reference.