Written Question · S2W-24667 · Session 2
Further to the answer to question S2W-21646 by Tavish Scott on 7 March 2006, why it took 85 days to respond, given that the decision to sus…
The question
To ask the Scottish Executive, further to the answer to question S2W-21646 by Tavish Scott on 7 March 2006, why it took 85 days to respond, given that the decision to suspend the Glenmayne scheme had already been taken at least 25 days prior to the question being lodged on 12 December 2005.
The answer
Following completion of theirdue diligence, officials concluded in November 2005 that the scheme should not betaken forward. There followed a period of discussion and review in order that Icould be satisfied that this decision was correct.
Transport Scotland hasthe operational responsibility for this area, and can be contacted for more informationif required.
Transport Scotland hasthe operational responsibility for this area, and can be contacted for more informationif required.
In the Official Report