Further to the answer to question S2W-18353 by Tavish Scott on 18 August 2005, when it expects to conclude its review of the Glenmayne sche…

Answered Asked by Derek Brownlee Con Lodged 12 Dec 2005

The question

To ask the Scottish Executive, further to the answer to question S2W-18353 by Tavish Scott on 18 August 2005, when it expects to conclude its review of the Glenmayne scheme.

The answer

Answered by Tavish Scott on 7 Mar 2006 · 85 days after it was lodged, 48 days after it was due

In developing the design forthis scheme since the original announcement in March 2003, a total of elevenoptions have been considered. In August 2003 consultants were appointed for thedevelopment of the scheme with a project brief being issued on 3 September 2003. ADivisional review of the development work on the scheme took place on 18 February 2005.
In June of 2005 followingfurther assessment, our consultants indicated that the economic analysis of allthe options failed to demonstrate the necessary value for money in taking thescheme forward. Before taking any decision, the scheme was reviewed byengineers from Scottish Borders Council in August 2005 and they confirmed ourearlier findings. In the light of this and the environmental impact which thescheme would have had, the decision was made in November 2005 not to take thescheme forward at this time. My officials will keep this section of the routeunder review and assess any future actions which may be required.