To ask the Scottish Executive, further to the answer to question S2W-23856 by Tavish Scott on 20 March 2006, what the combined cost would be of the Executive’s estimated cost of its planned on-line upgrade of the A80 plus the cost of the Auchenkilns interchange project and the cost of the millennium bridge.
The answer
The estimated cost ofconstructing the on line route is between £127 and £146 million. The cost of the Auchenkilns Junction was £25 million. The cost of the Millennium Bridge was£2.44 million.
Transport Scotland hasthe operational responsibility for this area, and can be contacted for moreinformation if required.