What steps it is taking to ensure that the precautionary principle promoted in government guidelines is being adhered to in the considerati…

Answered Asked by John Swinburne SSCUP Lodged 3 Jun 2005

The question

To ask the Scottish Executive what steps it is taking to ensure that the precautionary principle promoted in government guidelines is being adhered to in the consideration of requests by telecommunication operators to erect mobile phone masts.

The answer

Answered by Malcolm Chisholm on 14 Jun 2005 · 11 days after it was lodged, on time

The precautionary measures set out in National Planning Policy Guideline (NPPG)19: Radio Telecommunications for the most part do not relate to the consideration of individual applications for masts. So, for example, the audit of phone mast emissions is carried out by OFCOM, as is the maintenance of a database of mast sites, and is not tied to individual applications. Similarly, the Executive contributes to the Mobile Telecommunications and Health Research programme recommended by the Independent Expert Group and Mobile Phones. We do of course require planning applications to be accompanied by a declaration relating to compliance with the public exposure guidelines on radio frequency emissions issued by the International Commission on Non-ionising Radiation Protection, which were adopted as one of the precautionary measures, and policing of this is a matter for individual planning authorities.
We have already carried out a research project on the effects of the changes to planning legislation and guidance, including the introduction of NPPG 19 and Planning Advice Note (PAN) 62: Radio Telecommunications. This research (entitled Evaluation of Revised Planning Controls Over Telecommunications Development) was published in July 2004. We will also review the planning guidance, which we provisionally intend to do later next year. In the meantime we do monitor correspondence on these issues and have contacts with planning authorities, the industry and other Government Departments on the issues surrounding the rollout of this technology.
Copies of the documents mentioned in this reply are available from the Parliament’s Reference Centre (NPPG 19 Bib. number 15218, PAN 62 Bib. number 16043. and Research Bib. number 6703).

In the Official Report

No contribution in the Official Report cites S2W-17101 by reference.