Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S1W-33831 · Session 1

Further to the answer to question S1W-13764 by Angus MacKay on 5 April 2001, whether it will give up-to-date figures on how much was spent …

Answered Asked by David McLetchie Con Lodged 6 Feb 2003

The question

To ask the Scottish Executive, further to the answer to question S1W-13764 by Angus MacKay on 5 April 2001, whether it will give up-to-date figures on how much was spent on new capital investment in and refurbishment of its property in each year for which figures are available, broken down by project.

The answer

Answered by Andy Kerr on 18 Feb 2003 · 12 days after it was lodged, on time

The cost of refurbishment* (excluding maintenance, repairs and minor works) since 1 April 1996 is shown in the table:Project | 1996-97(£ million) | 1997-98(£ million) | 1998-99(£ million) | 1999-2000(£ million) | 2000-01(£ million) | 2001-02(£ million) | 2002-03 Estimated(£ million)
St Andrew's House: refurbishment | | | 1.26 | 6.26 | 4.20 | 5.86 |
Saughton House: Conversion of areas to provide additional staff accommodation | | 0.05 | 0.03 | 0.10 | 0.11 | 0.36 | 0.15
Pentland House: Conversion of areas to provide additional staff accommodation | | | | | | | 0.40
Strathearn House, Perth:New building fit-out | | | | | | | 0.65
Notes:Expenditure on refurbishment projects comprises both capital and current expenditure under present accounting rules.*Budgets are now set net of recoverable VAT and figures for previous years have been adjusted to take account of VAT recovered.

In the Official Report

No contribution in the Official Report cites S1W-33831 by reference.