Written Question · S1W-13764 · Session 1
How much was spent on new capital investment in and refurbishment of Scottish Executive property in each year for which figures are availab…
The question
To ask the Scottish Executive how much was spent on new capital investment in and refurbishment of Scottish Executive property in each year for which figures are available, specifying the amount spent in each year on each project.
The answer
Responsibility for property, including refurbishments, was delegated to the Scottish Office from Property Holdings (an Agency of the Cabinet Office) on 1 April 1996. These responsibilities were assumed by the Scottish Executive on 1 July 1999.The cost of refurbishment (excluding maintenance, repairs and minor works) since 1 April 1996 is shown in the table.Project | 1996-97 | 1997-98 | 1998-99 | 1999-2000 | 2000-01*Estimated
St Andrew's House Refurbishment | | | £1.47m | £7.07m | £4.94m
Saughton HouseConversion of areas to provide additional staff accommodation | | £0.06m | £0.04m | £0.12m | £0.02m
Expenditure on refurbishment projects comprises both capital and current expenditure under the present accounting rules.
St Andrew's House Refurbishment | | | £1.47m | £7.07m | £4.94m
Saughton HouseConversion of areas to provide additional staff accommodation | | £0.06m | £0.04m | £0.12m | £0.02m
Expenditure on refurbishment projects comprises both capital and current expenditure under the present accounting rules.