Further to the answer to question S1W-31958 by Malcolm Chisholm on 9 December 2002, whether #3,689,000 is still the forecast full-year over…

Answered Asked by Mary Scanlon Con Lodged 19 Dec 2002

The question

To ask the Scottish Executive, further to the answer to question S1W-31958 by Malcolm Chisholm on 9 December 2002, whether #3,689,000 is still the forecast full-year overspend by Argyll and Clyde Acute Hospitals NHS Trust in the light of the recent findings of the support team investigation into the trust's finances.

The answer

Answered by Malcolm Chisholm on 13 Jan 2003 · 25 days after it was lodged, on time

Argyll and Clyde Acute Hospitals NHS Trust is currently forecasting a year end overspend of £4,724,000, based on the November financial report.

In the Official Report

No contribution in the Official Report cites S1W-32792 by reference.